Construction project of Dry Phase1٫ South Pars Facility
Contract for the implementation of the phase development plan1٫ South Pars Gas Field by Pars Oil and Gas Company on behalf of the National Iranian Oil Company as the employer of the
Contract for the implementation of the phase development plan1٫ South Pars Gas Field by Pars Oil and Gas Company on behalf of the National Iranian Oil Company as the employer of the plan، To the consortium of Petropars Limitd (consortium leader), Petropars of Iran and Iran Marine Engineering and Manufacturing Company in 2 Khordad ۱۳. The location of the project is located in the Tombak area and about 210 km southeast of Bushehr port and with an area of about 218/5 hectares, between gas refineries Phases 11 and 12 South Pars. Currently, the project is a 5/99 percent physical development for 3 years, which is in the stage of commercial production, punching and closing of the following treaties.
The most important achievements of Phase 1٫ Project:
Management of all EPC stages by Petropars and domestic specialist forces, activity of more than 15,000 people at the peak of work, management of more than 1,200 internal and external contracts
Full launch of three a lot of gas in less than five months
Achieving early production in less than 70 months using reservoir gas during international sanctions
Record in paying workers' salaries and preventing labor tensions in payments
safety badge reception
Record in QC and environmental issues (including the early launch of Unit 129 for industrial wastewater treatment)
employment of more than 162 million people internal power clock in phase 19 plan
Installation of 55 thousand tons of metal structure
Installation of 40 thousand tons of fixed and rotary equipment
about 3 million inches diameter of pipe
About 7,200 km of electrical cable and precision instruments
Picture